MTSL Energies > Projects > ERTIII Grid Intensification under Package B. Lot 1B

Energy Meter Installation

Project Desciption

Engineering Design, Supply and Installation of 11kV/33kV lines and associated Low Voltage Networks for ERTIII Grid Intensification under Package B. Lot 1B: Gomba-Butambala districts. Construction of MV lines route length 140km, low voltage network of 192km and installation of 79 transformers.
REA-ERTIII/WRKS/19-20/00186/A

Project Starting DateJanuary 2020

Project EndMay 2021

SponsorWorld Bank & GOU