grid intensification under ERT III (52 schemes) for three lots; Lot 1: Central Service Territory (21 schemes)
Project Desciption
Design, supply and construction of 33kV medium voltage power lines and associated low voltage networks for grid intensification under ERT III (52 schemes) for three lots; Lot 1: Central Service Territory (21 schemes). MV route length of 10.41km, low voltage of 50km and installation of 21 Transformers.
REA-ERTIII/WRKS/17-18/00392a
Project Starting DateJanuary 2020
Project EndMay 2021
SponsorWorld Bank & GOU