Isimba Hydropower Projects-Grid
Project Desciption
EPC contract for Construction of Infrastructure Developments under the Community Development Action Plan (CDAP) for Isimba Hydropower Projects-Grid Extension and Electricity Reticulation Component in Kayunga and Kamuli Districts. Construction of Medium Voltage (33kV & 11kV) lines of 41.08km and associated Low Voltage lines of 98.25 km and installation of 59 distribution transformers in Kamuli and Kayunga districts in Uganda
UEGCL/WRKS/2019-2020/00008
Project Starting DateNovember 2021
Project EndIn Progress
SponsorGovernment Of Uganda